Update on CenterPoint work being done by Grid Source around Gladewater:
Work safety is CenterPoint Energy’s number one priority and the company works hard to improve and modernize its natural gas distribution system throughout our service territory.
The company has been replacing lines in Gladewater community as follows:
Total amounts to be completed is the breakdown of work for all 4 Phase in Gladewater,.
9095’ of 4” plastic pipe
4652’ of 2” plastic pipe
68 service will be replaced.
Expected date of completion will be 7/31/19 without any rain delays.
Contractors are still working in the areas below:
· Quitman and Main and areas near Railroad Tracks
· Dean St, by post office
· Ames St
Crews have approximately 600′ left to complete along with tie-ins as of 7/15/2019. The contractor is also starting cleanup at various locations.
With the exception of the permit for the railroad tracks, the expected date of completion will be 7/31/19 without any rain delays.
Any issues with construction or cleanup can be addressed by calling CenterPoint at 800-259-5544.